Modular worker accommodation solutions are factory-built housing units, such as container dormitories, combined camp buildings and portable cabins, that are delivered to a project site and assembled there, usually for construction, mining, energy and other remote work. They can shorten the time to occupancy and can be expanded in phases. The modules alone cannot ensure that a camp satisfies all compliance requirements. National legislation and internationally recognized standards stipulate the requirements for space per person, number of latrines and showers, as well as the system for the supply, disposal and management of water. Therefore, once the number of standard facilities required for a camp has been determined, the number and types of modules can be decided on.
Worker accommodations refer to the shelter for workers in sectors which include construction, oil and gas, mining, and other industries; they are usually constructed in areas where conventional housing is not available. Prefabricated and modular accommodations can be manufactured in the off-site facility and constructed on-site, and thus the construction of both the supplier’s operation and units can happen at the same time. ZN House describes four main types on its worker accommodation page: container dormitory buildings, modular combined accommodation buildings, portable accommodation cabins and temporary workforce housing. The site highlights such benefits as fast installation, versatility of design, easy relocation, inexpensive delivery, and slow camping development. On the other hand, the website lacks any data on the size, capacity, insulating properties, or fireproofing. Therefore, it would be best to view such claims merely as a beginning of the discussion.
Table 1. Modular worker accommodation types and what to confirm
| Type | Use described by the manufacturer | What to confirm in the quotation |
| Container dormitory buildings | Scalable workforce housing for construction camps, mining projects and infrastructure developments | Net floor area per room, beds per room, bunk layout, stacking limits |
| Modular combined accommodation buildings | Large camps that join sleeping blocks to dining halls, toilets, showers, recreation and offices | Which facilities are included, and fixture counts per building |
| Portable accommodation cabins | Remote job sites, industrial camps and emergency housing | Insulation, ventilation and heating or cooling for the climate |
| Temporary workforce housing | Rapid deployment with modular expansion and relocation | Foundation needs, connection details and reassembly method |
There is no single international rule for modular worker accommodation. The IFC and EBRD guidance note states that there are no comprehensive international regulations on workers’ accommodation and that compliance with national and local law is the basic requirement. It then collects the ranges that are commonly applied. The US OSHA standard for temporary labor camps is one legal example, and the IFC note quotes a Singapore code as another. The table sets them side by side.
Table 2. Accommodation benchmarks from three published sources
| Item | IFC/EBRD usual range | US OSHA 1910.142 (temporary labor camps) | Singapore code (as quoted by IFC/EBRD) |
| Sleeping floor area per person | 4 to 5.5 m² (or 10 to 12.5 m³) | 50 sq ft, about 4.6 m² | 4 m², or 3 m² with separate locker space, at 2.4 m height |
| Minimum ceiling height | 2.10 m | Not set in the cited text | Assumes 2.4 m |
| Toilets | 1 per 6 to 15 people | 1 per 15 people, minimum two units if shared | 1 per 15 male workers, with basin, urinal and bathroom |
| Urinals | 1 per 15 people | 1 per 25 men | Included in the per-15 ratio |
| Showers | 1 per 6 to 15 people | 1 head per 10 people | Bathroom per 15 male workers |
| Handwash basins | 1 per 6 to 15 people | 1 per 6 people in shared facilities | Basin per 15 male workers |
| Distance to toilets | 30 to 60 m from rooms | Within 200 ft, about 61 m, of each sleeping room door | Not stated |
| Drinking and washing water | 80 to 180 litres per person per day | Not covered in the cited text | Not stated |
The IFC/EBRD note also prefers single or double rooms over large dormitories, with 2 to 8 workers as the usual limit in shared rooms. It asks for a separate bed for each worker, at least 1 m between beds, minimized use of double-deck bunks and a ban on triple-deck bunks.
The following is a planning illustration for a modular worker accommodation camp, built from the table above. It is not a ZN House design, and it assumes a male workforce for the OSHA urinal ratio. Real figures depend on local law, gender mix and the camp’s operating pattern.
Table 3. Illustrative quantities for 200 workers (arithmetic, not a manufacturer specification)
| Quantity | Basis | Result for 200 workers |
| Net sleeping area | 4 to 5.5 m² per person | 800 to 1,100 m² |
| Workers in a 14.4 m² room (6.0 × 2.4 m, net) | 14.4 ÷ 4 and 14.4 ÷ 5.5 | 3 workers at 4.8 m² each, or 2 workers at 7.2 m² each |
| Rooms needed | 200 ÷ 3 or 200 ÷ 2 | 67 rooms at 3 per room, 100 rooms at 2 per room |
| Toilets | 1 per 15 to 1 per 6 | 14 to 34 units |
| Shower heads | OSHA 1 per 10; IFC/EBRD 1 per 15 to 1 per 6 | 14 to 34, with 20 at the OSHA ratio |
| Urinals | OSHA 1 per 25 men; IFC/EBRD 1 per 15 | 8 to 14 units |
| Water supply | 80 to 180 litres per person per day | 16,000 to 36,000 litres a day |
| Canteen floor area | 1 to 1.5 m² per worker, all seated at once | 200 to 300 m², or half if there are two sittings |
Two lessons follow for modular worker accommodation planning. Firstly, owing to the principle of allocating space properly, one standard-size room can accommodate only 2 or 3 workers, which makes the capacity of a work camp determined by standard measures and not by the number of beds that can be placed in the room. Secondly, the provision of such necessities as toilets and showers and the amount of water required are the main determinants of the size of a project site.
The IFC/EBRD note covers more than room size. Several factors in any modular worker accommodation camp sit outside the modules themselves and need planning with the site team:
A short checklist covers most of the risk when comparing modular worker accommodation offers:
How many workers can one modular worker accommodation unit house?
The answer is determined by net floor area and applicable guidelines. For example, one room having a net area roughly 14 m2 would accommodate two or three people at the IFC/EBRD rate range of between 4 and 5.5 m2 per individual. You should consult the vendor about the floor space and the maximum number of occupants per variant.
How many toilets and showers does a worker camp need?
According to several sources, the recommendations indicate that there should be between one toilet for about 15 people to one toilet for every 6 people. The information regarding showers is more scattered, indicating varying options of delivering one shower head for every 10 people to one head for 6 people. OSHA mentions the minimum requirement of at least one toilet per 15 people and two units in total; that can be supplemented by one shower head at least for every 10 people. Local laws receive the priority in making decisions which one of the suggested approaches is used.
Can modular worker camps be expanded or relocated?
According to ZN House, the buildings can be expanded in subsequent phases of the project as well as moved to a different location. Verify your model’s foundation type, utility connections, and the way it is assembled, as these factors will determine the extent of feasibility for the move or expansion of the structure.
To plan a modular camp, send your headcount, site location, climate and facility needs through the ZN House worker accommodation page to request a quotation.
Disclaimer
This article is general information. Product details come from ZN House’s own page and may change; confirm them in your quotation. The presented figures can serve as guidance and sample calculations based on some certain jurisdictions. The provided explanation is just illustrative. It does not represent any legal, public health, or engineering recommendations. The criteria for accommodation, fire protection, sanitary standards, and permits to operate are based on local legislation and particular construction projects.
Sources
ZN House – Worker Accommodation (manufacturer overview)
Sanitation is required at any place where humans reside, and the places where it is most required are usually the…
For developers, construction workers and the government, the true cost of a building is hardly concentrated just on the structure…
In some instances, sometimes a project cannot afford to wait some months before being put up. Mining camps, construction sites,…
Goods for housing and workspace are in demand for quicker than existing construction methods can build them. Remote work camps,…
Introduction There is an ever-increasing need for affordable, adaptable, and rapidly erected constructions within construction industry, infrastructure projects, and housing…
Short Answer Motel containers made of steel containers or freight containers act as accommodation in an area in which guests…